CHALLENGE TO BUILD

CHALLENGE TO BUILD

Coaling Baptist Church Facility Master Plan–10 Year
Adopted October 2015

Phase 1—Debt Retirement and Adjustments for Growth
Remodeling of former NL Fellowship Hall Bldg into Pre-School building
Furniture for Pre-School Building
Pay off of LaGrone, Tibbs and Perry Properties
Master Plan Development for Property
Gym Remodeling for Temp Sanctuary

Phase 2—New Education Building and Future Prep
Site Prep Work
Construction of 3 Story Education/Entrance
(15 classrooms, Childrens Worship/Activity area, offices, welcome center)
Furniture for Education Building
Elevator (Avg. cost is $25,000 a floor x 3 Floors)-$70,000-$80,000
Parking Lot Construction

Phase 3- New Sanctuary
Site Prep Work
Construction of 2 story Sanctuary
500-600 Seat Sanctuary, Nursery/Preschool space and Senior Adult classrooms, Choir room
Sanctuary Building Furniture
Parking Lot Construction

Phase 4- Building Updating
Sanctuary/Preschool Building Updating for classrooms/ministry space
Gymnasium Updating

Proposed Update to Pre-School Space of Coaling Baptist Church–Uploaded August 24th, 2015

Please send any comments, suggestions or ideas about this space to office@coalingbaptist.com. Include your name and phone number.

Suggested placement of classrooms is as follows.
1- Cribs
2-Crawlers
3-Toddlers
4- Preschool 1 Classroom
5-Preschool 2 Classroom

4webFellowHallRen.8.24

January 2017:
We are pleased to announce that as of Sunday, January 29, 2017, contributions towards The Master’s Plan are $129,145! The Pre-School facility has been completed and looks outstanding. See our progress!